According to reports, each of the three projects will be of 2x800 MW rating in Rajasthan's Kawai and Madhya Pradesh's Mahan.

BHEL will be involved in the supply of equipment and supervision of the erection and commissioning of these three power projects, as per reports.

The supply of equipment includes boilers, turbines, generators and associated auxiliaries, along with control and instrumentation, according to media reports.

Government-run BHEL will have to complete the Kawai Phase-II project in 49 months, Kawai Phase-III project in 52 months and Mahan Phase-III project in 55 months, reports said.