Severe floods devastate state's electricity system; Restoration efforts underway amidst challenges
Severe floods devastate state's electricity system; Restoration efforts underway amidst challenges
The state’s electricity infrastructure has been severely damaged following catastrophic flooding. With engineers, officials, and staff from the Tripura State Electricity Corporation Limited (TSECL) working tirelessly to restore power. Despite round-the-clock efforts, full restoration remains challenging, particularly in the South and Gomati districts, which have been hit hardest by the floods.
TSECL through a press statement said that in the South district, progress has been notable, with electricity re-established in 164 out of 195 Gram Panchayats and Village Committees across Sabroom, Santirbazar, and Belonia.
However, ongoing difficulties include areas without road connectivity and extensive water accumulation that makes it difficult to erect new electricity poles. Efforts are being focused on reconnecting the remaining 31 Gram Panchayats and Village Committees part, with support from both district and sub-divisional administrations.
In the Gomati district, power has been largely restored to Udaipur, though Amtali and Banduar in the Tepania area remain without service due to severe water logging. Additional complications have arisen in Shalagra Beri, Rajdhar Nagar, and Fakirbari where water accumulation continues to obstruct restoration efforts. Most of Udaipur division has regained power except for Purba Mirza Switchgate Para, Radha Banshi Para, and Chhota Gangrai, where service remains interrupted.
The Amarpur division has faced the most severe impacts, with extensive water logging and fallen trees hampering restoration. Despite these obstacles, TSECL workers have successfully reactivated power in many areas. The corporation is in ongoing communication with the Gomati District and Amarpur Sub-Divisional Administrations to expedite service restoration in the affected regions.
As the state battles the aftermath of these unprecedented floods, TSECL remains committed to overcoming the challenges and restoring electricity as swiftly as possible, with continued cooperation from local authorities essential for progress.
NEH Report
Senior Staff Reporter at Northeast Herald, covering news from Tripura and Northeast India.
Related Articles

Assam Rifles commemorates 150 years of Vande Mataram
Assam Rifles commemorates 150 years of Vande Mataram

Tripura journalist Dr Bishwendu Bhattacharjee to attend 30th World Climate Summit in Brazil as part of Indian delegation
Dr Bhattacharjee will attend the conference as the representative of the news agency UNI

Global NHRC body fails to take action on non-existent Bangladesh NHRC to save the image of Dr Yunus
Global NHRC body fails to take action on non-existent Bangladesh NHRC to save the image of Dr Yunus

Teachers’ Council, IQAC and NCC Unit of MBB College organised an awareness programme on Vigilance Week
Teachers’ Council, IQAC and NCC Unit of MBB College organised an awareness programme on Vigilance Week
Latest News

'If a war breaks out...': Taliban warns Pakistan after Istanbul peace talks end in deadlock
Banga Bhushan, DSP rank, Rs. 34 lakh reward and more! Eden Gardens celebrates World Cup hero Richa Ghosh

Mamdani’s New York victory sparks concern in Israel over shifting US sentiments

Fortifying 'Chicken's Neck'? Indian Army sets up military garrisons near Bangladesh border